Deliveries to construction sites: planning the arrival

In brief

A construction site's access and unloading facilities may change rapidly. A delivery that worked last week is not automatically straightforward today.

Practical example

Large building elements arrive while the site's crane is committed elsewhere. The transporter may be unable to unload despite reaching the address.

Name a receiving contact

Provide a person who knows the current site layout and can answer the driver's questions. For larger deliveries, an address without an operational contact is rarely sufficient. Clarify who can direct the vehicle to the correct unloading area.

Check access on the delivery day

Temporary roads, entrances and standing areas may change rapidly. Ground bearing, headroom, bends, gates, safety induction and any protective equipment requirements should be known. A long or heavy vehicle may need a different entrance.

Coordinate unloading

A crane, telehandler or forklift may be shared with other site tasks. Clarify its availability, capacity and operator before the delivery is confirmed. Moving goods around the site after unloading is a separate operation unless included by agreement.

Changes and waiting time

If a site cannot receive the load or needs a different delivery slot, tell the transport contact promptly. Good planning reduces the risk of vehicles blocking work areas or material being left in an unsuitable location.

Information to confirm before booking

  • Receiver and telephone number
  • Confirmed entrance and stopping area
  • Unloading equipment and operator booked
  • Any site access requirements clarified
  • Plan for changes to the delivery window